VBHC Palmhaven 2 – Construction Updates

The VBHC Palm Haven Project Phase II has obtained all necessary approvals from BDA.NOCs from BESCOM, Pollution Control Board and Panchayat have also been obtained.

WE ARE PLEASED TO CONFIRM THE FOLLOWING CONSTRUCTION PROGRESS:

  • C1 Block: 9th Floor super structure works in progress.
  • C2 Block: 6th Floor super structure works in progress.
  • C3 Block: 6th Floor super structure works in progress.

The status of construction as on 17th November 2016 is as follows:

LEVELS C1 C2 C3
Excavation Tick Tick Tick
Footing Tick Tick Tick
Basement Tick Tick Tick
Stilt Tick Tick Tick
2nd Floor Tick  Tick Tick
4th Floor  Tick Tick Tick
6th Floor  Tick  6th Work In Progress 6th Work In Progress
8th Floor Tick
10th Floor  9th Work In Progress
12th Floor
14th Floor
16th Floor
18th Floor
20th Floor
Completion of Vitrified Tiling
CP & Sanitary Fitting
On Possession