VBHC Greenglade – Construction Updates

Construction at VBHC Evergreen A project started in early 2013 and has been going at a smooth pace. There were initial delays due to heavier than expected monsoon; however, now project is progressing as per schedule. VBHC Evergreen A has 8 G+4 blocks A1, A2, A3, A4, A5, A6, A7, and B1. Construction of each block can be divided broadly in four stages: Excavation, Sub-structure (grade slab), Super-structure (ground floor to terrace), and Finishing (water proofing, tiles, kitchen works, lifts, etc.). We have completed excavation, Sub-structure (grade slab), Superstructure and finishing of all the blocks. Possession of all the blocks has been given to the customers. UG sump and STP are operational. One of the major attractions is the triangular landscape made on the centre of the projects imparts poshness to the project.

ROADS

The main arterial road is completed and is open for vehicular movements. Internal road that is made up of pavers around the landscape is adding to the beauty of the parcel is also completed and residents are using it.

BUILDINGS

There has been steady progress in getting all the blocks ready for possession. Here are the individual Block wise updates:

  • A1 Block (Possession) – Possession given to the customers.
  • A2 Block (Possession) – Possession given to the customers.
  • A3 Block (Possession) – Possession given to the customers.
  • A4 Block (Possession) – Possession given to the customers.
  • A5 Block (Possession) – Possession given to customers.
  • A6 Block (Possession) – Possession given to customers.
  • A7 Block (Possession) – Possession given to the customers.
  • B1 Block (Possession) – Possession given to the customers.

OTHER INFRASTRUCTURES

  • Internal road work Completed.
  • Main Road Completed.
  • UG Sump Operational for existing residents.
  • STP It is operational for existing customers.
  • Transformer Yard Erection commissioning of transformer and DG completed.
  • Shopping Complex and Community hall It is completed and is open for residents use.
  • Play Area Equipments installed and are used by the residents.

MODEL APARTMENTS

  • Fully furnished model apartments are ready and we encourage you to come and visit it and interact with us on-site.