• info@vbhc.com
  • Call Us: 1800 103 8242 (India) | +971 5882 29670 (Dubai)

VBHC Greenwoods – Construction Updates

Construction at VBHC Greenwood project started in October 2015 and has been going at a smooth pace. VBHC Greenwood has 8 G+4 blocks “ A1, A2, A3, B1, B2, B3, C1 and C2″. Construction of each block can be divided broadly in four stages: Excavation, Sub-structure (grade slab), Super-structure (ground floor to terrace), and Finishing (water proofing, tiles, kitchen works, lifts, etc.

WE ARE PLEASED TO CONFIRM THE FOLLOWING CONSTRUCTION PROGRESS:

  • B2 Block: Superstructure Completed & Finishing activities are in progress.
  • C1 Block: Finishing Works are in progress.
  • A3 Block: 4th Floor in progress.
  • A2 Block: Substructure work is completed.
  • A1 Block: Substructure work is completed.
  • B1 Block: Superstructure Completed.
  • C2 Block: Superstructure Completed.
  • B3 Block:4th Floor in progress.

The status of construction as on 21st March 2017 is as follows:

LEVELS A1 A2 A3 B1 B2 B3 C1 C2
Excavation Tick Tick Tick Tick Tick Tick Tick Tick
Footing Tick Tick Tick Tick Tick Tick Tick Tick
Grade Slab Tick Tick Tick Tick Tick Tick Tick Tick
Ground Tick Tick Tick Tick Tick Tick
1st Floor Tick Tick Tick Tick Tick  Tick
2nd Floor Tick  Tick Tick  Tick Tick Tick
3rd Floor  Tick  Tick Tick  Tick Tick Tick
4th Floor  In Progress Tick Tick  In Progress Tick  Tick
Completion of Vitrified Tiling In Progress In Progress
CP & Sanitary Fitting In Progress  In Progress
On Possession