VBHC 47 Rowland Park – Construction Updates

VBHC 47 ROWLAND PARK construction status as of 13 Jun 2023:

E Block : E1 – E8 :
Excavation, Foundation work, Ground floor slab & 1st floor slab works are completed. Masonry work, door frame fixing, waterproofing & floor finishing work completed. Internal and external painting WIP

E Block : E9 – E16 :
Excavation, Foundation work, Ground floor slab & 1st floor slab works are completed. Masonry work and door frame fixing were also completed. Waterproofing work completed and floor tiling and internal painting work in progress.

F Block : F1 – F8 :
Excavation, Foundation work, Ground floor slab & 1st floor slab works are completed. Masonry work, door frame fixing and waterproofing work also completed. Flooring tiling is in progress.

F Block : F9 – F16 :
Excavation, Foundation works, Ground floor slab & 1st floor slab works are completed. Masonry work and door frame fixing and waterproofing work were also completed. Flooring tiling is in progress.

G Block : G1 – G8 :
Excavation, Foundation works, Ground floor slab & 1st floor slab works are completed. Masonry work and door frame fixing are completed.

G Block : G9 – G16 :
Excavation, Foundation works, Ground floor slab & 1st floor slab works are completed. Masonry work and door frame fixing are WIP.

H Block : H1 – H4 :
Excavation, Foundation work, Ground floor slab & 1st floor slab works are completed. Masonry work and door frame fixing are WIP.

I Block : I1 – I5 :
Excavation, Foundation works & Ground floor slab & First floor slab work completed. Masonry work and door frame fixing work are completed.

J Block : J1 – J8 :
Excavation, Foundation works & Ground floor slab & First floor slab work completed. Masonry and door frame fixing work is completed. Waterproofing WIP.

 

Disclaimer

All project information and details displayed on the site, including but not limited to the information and details contained in project related materials that you may download are for information purposes only and do not constitute an offer under any law for the time being in force. The Company shall not be liable to you for any decisions you may take as a result of or on the basis of such information and encourages you to contact the Company directly for up-to-date and accurate information.

The imagery used on the website and brochures are indicative only. Photographs of interiors, surrounding views and location may have been digitally enhanced or altered and do not represent actual views or surrounding views. These photographs are indicative only.

Changes may be made during the development of a real estate project and standard fittings and specifications are subject to change without notice. Standard fittings and finishes are subject to availability and vendor discretion. Fittings, finishes and fixtures shown in the images contained in this brochure are not standard and will not be provided as part of an apartment. The information contained herein is believed to be correct but is not guaranteed. Prospective purchasers should make and must rely on their own enquiries. The colors of the buildings are indicative only. This website and all brochures are a guide only and do not constitute an offer or contract.

Disclaimer: The images used on the website and brochures are indicative only. Photographs of interiors, surrounding views and location may have been digitally enhanced or altered and do not represent actual views or surrounding views. These photographs are indicative only.